Meeting documents

  • Meeting of This Policy Advisory Group is not open to the public, Resources Policy Advisory Group, Tuesday, 25th September, 2018 6.00 pm (Item 48.)

Minutes:

Members received a report which contained the final business case for the design and construction of the redevelopment of Gerrards Cross Police Station scheme and sought Members approval to progress the project. Planning permission was issued on 17 August 2018 subject to 22 conditions, of which 10 had to be discharged prior to commencement. The redevelopment would be for 34 apartments, of which 20 would be private rent apartments and 14 affordable rent apartments to meet the 40% affordable housing requirement.

 

The current estimated cost was £8.3m as set out in section 6 of the report. Mitigation measures had been arranged to minimise the risk of: asbestos removal; ecology (bat); contamination; statutory services; planning conditions to discharge. The cost did not include project risks such as archaeology, ordinance, judicial review cost and de-contamination beyond the provisional sum allowance.

 

The Next steps were outlined in point 17.1 of the report with the ultimate completion and handover scheduled for 1 May 2020.

 

The PAG was advised that the business case estimated the development would break even in year 12 and start to turn a profit from there. Members agreed that this was an exciting project which would meet the Council’s affordable housing aspiration and benefit residents.

 

It was clarified that a housing association would receive a management fee built in to the planned costs of approximately £60k and as part of that agreement the housing association would be responsible for any damage caused to properties.

 

Members queried the increase in cost prediction from June 2018. It was explained that the finalised figures included figures for dealing with the mitigation measures as noted above and a further contingency sum of £200k was included. It was added that a further asbestos survey would be completed to establish the extent and instruct removal measures. Thames Valley Police had agreed to pay up to £200k of any de-contamination costs.

 

The PAG was clear that overspend on the project should not occur unless absolutely unavoidable. The PAG was advised that once the agreement had been signed with the contractor the majority of risks then became their responsibility which would avoid unexpected cost increases to the Council.

 

It was explained that as it was intended that the property would be held in order to make a financial return, the Council were required to do this via a company. It was therefore proposed to dispose of the development to Consilio Property Limited, a wholly owned company set up by SBDC, once it was completed.

 

Having considered the advice of the Policy Advisory Group, the Portfolio Holder agreed to RECOMMEND to Cabinet:

 

1.      To approve the final business case for the project.

2.      That Members note the total proposed spend of £8.331m, which will be funded from the current approved Capital Budget for this scheme.

3.      That the Head of Environment be authorised to conclude the delivery agreement between Wilmot Dixon and the Council for the construction phase.

4.      That the Head of Finance be authorised to carry out the necessary agreements to obtain the loan finance.

5.      That the Head of Environment be authorised to negotiate and conclude any necessary agreements to allow the development to proceed through to completion and note that the Head of Environment has exercised his delegated authority to make an application to the Secretary of Transport for a stopping up order pursuant to Section 247 of the Town and Country Planning Act 1990.

6.      That the Director of Resources be authorised to dispose of the development to Consilio (the Council’s wholly owned subsidiary).

 

 

Note 2: Councillor Dhillon left the meeting at 7.01 p.m.  

Supporting documents: